Finished my van upgrade to more complexity (or is it just a higher toy level??).
Not really a bad job considering that the van was not pre-wired for solar, nor that there were roof attachments for solar, or that the van top is a Sportsmobile Penthouse Top (moves up and down).
Added two 100 watt panels and a MPPT charge controller. Project tooks two days to complete once I had the panels.
Not really a bad job considering that the van was not pre-wired for solar, nor that there were roof attachments for solar, or that the van top is a Sportsmobile Penthouse Top (moves up and down).